PROBLEM 1:
a. 9.0 m³/s
b. 16.5 m³/s
c. 1.5 m³/s
d. 16.3 m³/s
Correct Answer: A
Step-by-Step Solution:
To find the peak runoff, we use the Rational Method formula in metric units:
1. Identify Given Data:
- • C (Runoff Coefficient) = 0.4
- • I (Rainfall Intensity) = 101.25 mm/hr
- • A (Area) = 80 hectares
2. Perform Calculation:
Q = 3240 / 360
Q = 9.0 m³/s
Final Result: a. 9.0 m³/s
PROBLEM 2 :
MARIKINA WATERSHED (500 SQ. KM.) HAD AN AVERAGE CN VALUE OF 65 IN 1970 WITH A STORM DEPTH OF 100 MM. AFTER 30 YEARS, THE SAME STORM OCCURRED BUT THE CN VALUE INCREASED TO 84 DUE TO LAND USE CHANGE. WHAT IS THE PERCENTAGE CHANGE IN THE DEPTH OF RUNOFF?
a. 1.33%
b. 80%
c. 41%
d. 133%
Correct Answer: D (approx. 133%)
Step-by-Step Solution:
We use the SCS Runoff Equation where S = (25400 / CN) - 254 and Q = (P - 0.2S)² / (P + 0.8S).
1. Calculate for 1970 (CN = 65):
Q1 = (100 - 0.2×136.77)² / (100 + 0.8×136.77) = 25.32 mm
2. Calculate for 30 Years Later (CN = 84):
Q2 = (100 - 0.2×48.38)² / (100 + 0.8×48.38) = 58.98 mm
3. Calculate Percentage Change:
% Change = [(58.98 - 25.32) / 25.32] × 100
% Change = 1.329 × 100 = 132.9%
Final Result: Approximately 133%
PROBLEM 3:
a. 10 lps
b. 20 lps
c. 30 lps
d. 40 lps
Correct Answer: C
Step-by-Step Solution:
To solve this, we first find the velocity (v) of the water leaving the pipe using the trajectory coordinates, then apply the discharge formula Q = A × v.
1. Solve for Velocity (v):
v = 1.5 × √(9.81 / (2 × 0.8))
v = 1.5 × √(6.13125) ≈ 3.714 m/s
2. Calculate Pipe Area (A):
Area = (π / 4) × (0.1016)² ≈ 0.008107 m²
3. Solve for Discharge (Q):
Q = 0.008107 × 3.714 × 1.0
Q ≈ 0.03011 m³/s = 30.11 lps
Final Result: c. 30 lps
PROBLEM 4:
a. 10 m
b. 8 m
c. 20 m
d. 16 m
Correct Answer: B
Step-by-Step Solution:
The width of the terrace (W) can be determined using the relationship between the vertical interval (VI), the land slope (S), and the batter slope (u).
1. Identify Given Data:
- • Vertical Interval (VI) = 2 meters
- • Land Slope (S) = 20% = 0.20
- • Batter Slope (u) = 1:1 = 1.0
2. Use the Terrace Width Formula:
3. Perform Calculation:
W = 10 - 2
W = 8 meters
Final Result: b. 8 m
PROBLEM 5:
a. 48.5 m/s
b. 3.50 m/s
c. 2.15 m/s
d. 4.85 m/s
Correct Answer: D
Step-by-Step Solution:
To find the theoretical velocity of flow from an orifice, we use Torricelli's Theorem.
1. Identify Given Data:
- • Head (h) = 120 cm = 1.2 meters
- • Acceleration due to gravity (g) = 9.81 m/s²
2. Use the Theoretical Velocity Formula:
3. Perform Calculation:
v = √(23.544)
v = 4.852 m/s
Final Result: d. 4.85 m/s
PROBLEM 6:
a. 1.0 HP
b. 2.0 HP
c. 3.0 HP
d. 1.5 HP
Correct Answer: B
Step-by-Step Solution:
1. Calculate Total Dynamic Head (TDH):
TDH = Static Head + Friction Loss = 6m + 1.6m = 7.6 meters
2. Convert Flow Rate to Liters per Second (lps):
3. Calculate Water Horsepower (WHP):
4. Calculate Brake Horsepower (BHP):
BHP = 1.0 / (0.50 × 1.0)
BHP = 2.0 HP
Final Result: b. 2.0 HP
PROBLEM 7:
a. 0.851 m³/s
b. 0.935 m³/s
c. 1.123 m³/s
d. 0.568 m³/s
Correct Answer: B
Step-by-Step Solution:
1. Calculate Geometric Properties (Trapezoidal Section):
Wetted Perimeter (P) = b + 2y√(1 + z²) = 0.6 + 2(0.5)√(1 + 1²) = 2.014 m
Hydraulic Radius (R) = A / P = 0.55 / 2.014 = 0.273 m
2. Apply Manning's Equation for Velocity (v):
v = (1 / 0.035) × (0.273)^(2/3) × (0.02)^(1/2)
v = 28.57 × 0.421 × 0.1414 = 1.701 m/s
3. Calculate Capacity (Discharge, Q):
Q = 0.55 m² × 1.701 m/s
Q = 0.935 m³/s
Final Result: b. 0.935 m³/s
PROBLEM 8:
IF THE IMPELLER SPEED OF A CENTRIFUGAL PUMP IS INCREASED FROM 1800 RPM TO 2340 RPM, THE RESULTING POWER WILL BE HOW MANY TIMES THE ORIGINAL?
a. 1.690
b. 2.197
c. 1.091
d. 1.140
Correct Answer: B
Step-by-Step Solution:
According to the Pump Affinity Laws, the power (P) required by a pump is proportional to the cube of the impeller speed (N).
1. Identify the Given Speeds:
- • Original Speed (N1) = 1800 rpm
- • New Speed (N2) = 2340 rpm
2. Use the Power Affinity Ratio Formula:
3. Perform Calculation:
Ratio = (1.3)³
Ratio = 1.3 × 1.3 × 1.3 = 2.197
Final Result: b. 2.197
PROBLEM 9:
A SPRINKLER SPACING OF 12 X 18 M AND AN APPLICATION RATE OF 10 MM/HR WILL REQUIRE A SPRINKLER WITH A CAPACITY OF:
a. 0.6 lps
b. 6 lps
c. 3.6 lps
d. 36 lps
Correct Answer: A
Step-by-Step Solution:
The required capacity of a single sprinkler is calculated by multiplying the area covered by the sprinkler (spacing) by the desired application rate.
1. Identify Given Data:
- • Spacing (S1 × S2) = 12 m × 18 m = 216 m²
- • Application Rate (I) = 10 mm/hr = 0.010 m/hr
2. Calculate Discharge in m³/hr:
Q = 216 m² × 0.010 m/hr = 2.16 m³/hr
3. Convert to Liters per Second (lps):
Q (lps) = 2160 / 3600
Q = 0.6 lps
Final Result: a. 0.6 lps
PROBLEM 10:
a. 150 m³/hr
b. 200 m³/hr
c. 175 m³/hr
d. 140 m³/hr
Correct Answer: D
Step-by-Step Solution:
1. Calculate Daily Water Depth Requirement:
In meters: 9 mm = 0.009 m/day
2. Calculate Total Volume for 5 Days:
Volume = Area × Depth × Days
Volume = 80,000 m² × 0.009 m/day × 5 days = 3,600 m³
3. Adjust for Irrigation Efficiency (75%):
Gross Volume = 3,600 m³ / 0.75 = 4,800 m³
4. Calculate Discharge (Q) for 24-hour delivery:
Q = 4,800 m³ / 24 hours
Q = 200 m³/hr
Final Result: b. 200 m³/hr
Note: Based on the calculation steps, Choice B is the correct numerical result.
PROBLEM 11:
12,500 CUBIC METERS OF WATER WAS DELIVERED TO A 10 HA FARM FOR THE MONTH OF JUNE. CONSUMPTIVE USE IS 8 MM/DAY AND EFFECTIVE RAINFALL IS 150 MM. WHAT IS THE IRRIGATION EFFICIENCY?
a. 32%
b. 87%
c. 72%
d. 52%
Correct Answer: C
Step-by-Step Solution:
1. Calculate Total Consumptive Use (CU) for June:
Total CU = 8 mm/day × 30 days = 240 mm
2. Calculate Net Irrigation Requirement (NIR):
NIR = 240 mm - 150 mm = 90 mm
3. Convert NIR Depth to Volume (Net Volume):
Net Volume = 100,000 m² × 0.090 m = 9,000 m³
4. Solve for Irrigation Efficiency (Ea):
Ea = (9,000 m³ / 12,500 m³) × 100
Ea = 0.72 × 100 = 72%
Final Result: c. 72%
PROBLEM 12:
a. 25.32 ft.
b. 32.41 ft.
c. 33.39 ft.
d. 35.12 ft.
Correct Answer: B
Step-by-Step Solution:
1. Calculate Water Horsepower (WHP):
WHP = 5 HP × 0.65 = 3.25 HP
2. Use the HP formula to find Head in meters:
3.25 = (25 × H) / 76
H = (3.25 × 76) / 25 = 9.88 meters
3. Convert Meters to Feet:
H (ft) = 32.414... ft
Final Result: b. 32.41 ft.
PROBLEM 13:
a. 73.33 mm/day (Up)
b. 73.33 mm/day (Down)
c. 14 mm/day (Up)
d. 14 mm/day (Down)
Correct Answer: B
Step-by-Step Solution:
1. Calculate Hydraulic Gradient (i):
i = (164 m - 152 m) / 18,000 m
i = 12 / 18,000 = 0.0006667
2. Calculate Darcy Velocity (v):
v = 11.0 m/day × 0.0006667 = 0.007333 m/day
3. Calculate Actual (Seepage) Velocity (Vs):
Vs = 0.007333 / 0.10 = 0.07333 m/day
4. Convert to mm/day and Determine Direction:
Final Result: b. 7 mm/day towards the down-gradient point.
Water always flows from high head (164m) to low head (152m), which is the down-gradient direction.
PROBLEM 14:
a. 4 hp
b. 3.5 hp
c. 4.5 hp
d. 5 hp
Correct Answer: A
Step-by-Step Solution:
1. Calculate Water Horsepower (WHP):
WHP = (15 × 7) / 76
WHP = 105 / 76 = 1.38 HP
2. Calculate Brake Horsepower (BHP):
BHP = 1.38 / 0.60 = 2.30 HP
3. Calculate Prime Mover Rating (PMR):
PMR = 2.30 / 0.55
PMR = 4.18 HP
Final Result: a. 4 hp (nearest standard rating)
PROBLEM 15:
a. 0.250 lps
b. 0.375 lps
c. 0.500 lps
d. 0.250 lps
Correct Answer: A
Step-by-Step Solution:
The discharge of a sprinkler nozzle is determined by the application rate required to deliver the water depth over the specified time for the area covered by one sprinkler.
1. Calculate Required Application Rate (I):
Time (T) = 6 hours
Rate (I) = d / T = 150 mm / 6 hrs = 25 mm/hr
2. Calculate Area per Sprinkler (As):
Area = 36 m²
3. Solve for Discharge (q):
q = (36 m² × 0.025 m/hr) / 3600 sec/hr
q = 0.9 / 3600 = 0.00025 m³/s
4. Convert to Liters per Second (lps):
Final Result: a. 0.250 lps
PROBLEM 16:
a. 1.1 li
b. 1.9 li
c. 12 li
d. 21 li
e. 64 li
Correct Answer: D
Step-by-Step Solution:
We use the principle of conservation of mass, where the amount of dye remains constant before and after dilution.
1. Identify Given Data:
- • Initial Volume (V1) = 15 liters
- • Initial Concentration (C1) = 12%
- • Final Concentration (C2) = 5%
2. Use the Dilution Formula:
3. Solve for Final Volume (V2):
0.12 × 15 = 0.05 × V2
1.8 = 0.05 × V2
V2 = 1.8 / 0.05 = 36 liters
4. Calculate Amount of Water Added:
Water Added = 36 - 15
Water Added = 21 liters
Final Result: d. 21 li
PROBLEM 17:
a. 1 hr
b. 2 hr
c. 3 hr
d. 3.5 hr
e. 2.5 hr
Correct Answer: B
Step-by-Step Solution:
Since the planes are traveling in opposite directions, the distance between them increases at a rate equal to the sum of their speeds.
1. Calculate the Combined (Relative) Speed:
Relative Speed = 480 mph + 520 mph
Relative Speed = 1,000 mph
2. Use the Time Formula:
3. Solve for Time:
t = 2 hours
Final Result: b. 2 hr
PROBLEM 18:
a. 64.5 m
b. 20 m
c. 15.5 m
d. 12.4 m
e. 18 m
Correct Answer: C
Step-by-Step Solution:
If a strip of width x is plowed around the field, the unplowed area in the center remains a rectangle with dimensions (100 - 2x) and (60 - 2x).
1. Set up the Area Equation:
Two-thirds plowed = 2/3 × 6,000 = 4,000 m²
One-third unplowed = 1/3 × 6,000 = 2,000 m²
2. Formulate the Algebraic Equation:
3. Simplify and Solve for x:
4x² - 320x + 4,000 = 0
Divide by 4: x² - 80x + 1,000 = 0
4. Apply the Quadratic Formula:
x = [80 ± √(6400 - 4000)] / 2
x = [80 ± 48.99] / 2
x₁ = 64.5 m (not possible) , x₂ = 15.5 m
Final Result: c. 15.5 m
PROBLEM 19:
a. 200 lb.
b. 182 lb.
c. 291 lb.
d. 625 lb.
e. 198 lb.
Correct Answer: C
Step-by-Step Solution:
The total hydrostatic force (F) on a vertical surface is calculated by multiplying the specific weight of water (62.4 lb/ft³), the depth to the centroid (h-bar), and the total area (A).
1. Calculate the Area (A):
Area = [(3 + 2) / 2] * 2 = 5.0 sq. ft.
2. Locate the Centroid Depth (h-bar) from the Top:
h-bar = (2 / 3) * [(3 + 2*2) / (3 + 2)]
h-bar = (0.667) * (7 / 5) = 0.933 ft.
3. Solve for Total Force (F):
Force = 62.4 * 0.933 * 5.0
Force = 291.1 lbs
Final Result: c. 291 lb
PROBLEM 20:
a. 117 ∏
b. 36 ∏
c. 136 ∏
d. 27 ∏
e. 729 ∏
Correct Answer: A
Step-by-Step Solution:
To find the volume from the rate of change (derivative), we need to integrate the function with respect to h from 0 to 3 meters.
1. Set up the Integral:
2. Expand the Squared Term:
V = ∏ ∫ (4h² + 12h + 9) dh
3. Integrate:
4. Evaluate at h = 3:
V = ∏ [ (4/3)(27) + 6(9) + 27 ]
V = ∏ [ 36 + 54 + 27 ]
V = 117 ∏ cu. meters
Final Result: a. 117 ∏ cu. meters
PROBLEM 21:
a. L = 17.4 m
b. L = 0.0174 m
c. L = 1.74 m
d. L = 0.174 m
Correct Answer: c. L = 1.74 m
Step-by-Step Solution:
Simplify this scenario by applying the maximum discharge condition to the standard weir formula to find the minimum length required to keep the depth within bounds.
1. Identify the Given Values:
Maximum allowable head (Hmax) = L / 3
2. Apply the Francis Weir Equation:
1.415 = 1.84 * L * (L / 3)1.5
3. Simplify and Solve for L:
1.415 = (1.84 / 5.196) * L2.5
1.415 = 0.3541 * L2.5
4. Calculate the Final Value:
L2.5 = 3.996
L = (3.996)1 / 2.5
L = 1.74 meters
Final Result: c. L = 1.74 m
PROBLEM 22:
a. 60
b. 62
c. 92
d. 67
Correct Answer: d. 67
Step-by-Step Solution:
Water application efficiency (Ea) measures how much of the water delivered to the field is actually stored in the root zone for plant use.
1. Calculate the Water Stored in the Root Zone:
Depth stored = 1 foot
Volume Stored = 80 acres * 1 foot = 80 acre-feet
2. Calculate the Total Water Applied to the Field:
Time (t) = 4 hours = 14,400 seconds
Total Volume Applied = 360 cfs * 14,400 seconds = 5,184,000 cubic feet
3. Convert the Applied Volume to Acre-Feet:
Volume Applied = 5,184,000 / 43,560 = 119.01 acre-feet
4. Compute Application Efficiency (Ea):
Ea = (80 / 119.01) * 100
Ea = 67.22% ≈ 67%
Final Result: d. 67
PROBLEM 23:
a. 48
b. 35
c. 50
d. 54
Correct Answer: a. 48
Step-by-Step Solution:
Since the copper ore being added contains no zinc (0% zinc), the total amount of pure zinc in the mixture stays exactly the same. Adding the ore simply increases the total weight of the alloy, which dilutes the zinc concentration from 40% down to 25%.
1. Calculate the Amount of Pure Zinc in the Initial Alloy:
Zinc Percentage = 40%
Pure Zinc = 80 * 0.40 = 32 kgs
2. Set up the Mixture Balance Equation:
Total final weight of the new alloy = 80 + x
Final target zinc concentration = 25% (0.25)
3. Formulate the Mathematical Expression:
32 = 0.25 * (80 + x)
4. Solve for x:
32 - 20 = 0.25x
12 = 0.25x
x = 12 / 0.25
x = 48 kgs
Final Result: a. 48
PROBLEM 24:
a. 1.421 t/m2; 0.499 t/m2
b. 71.25 t/m2; 24.7 t/m2
c. 7.125 t/m2; 2.47 t/m2
d. 14.21 t/m2; 4.99 t/m2
Correct Answer: d. 14.21 metric tons/sq. m; 4.99 metric tons/sq. m.
Step-by-Step Solution:
Note: Standard masonry/concrete for gravity dams typically weighs 2.4 tons/m3.
1. Compute the Total Weight of the Dam (W):
W = 0.5 * Base * Height * unit weight of concrete
W = 0.5 * 6 m * 8 m * 2.4 tons/m3 = 57.6 tons
2. Compute the Total Horizontal Hydrostatic Force (P):
P = 0.5 * unit weight of water * Height2
P = 0.5 * 1.0 * 82 = 32.0 tons
3. Determine Eccentricity (e) about the Center of the Base:
The weight acts at 1/3 of the base from the vertical face (2 m), which is 1 m from the center.
The water pressure acts at H/3 from the base (8/3 m).
Mcenter = P * (8 / 3) - W * 1
Mcenter = 32.0 * (8 / 3) - 57.6 * 1 = 85.333 - 57.6 = 27.733 ton-m
e = Mcenter / W = 27.733 / 57.6 = 0.4815 meters
4. Compute Foundation Pressures:
q = (57.6 / 6) * (1 ± (6 * 0.4815) / 6)
q = 9.6 * (1 ± 0.4815)
qmax = 9.6 * 1.4815 = 14.22 t/m2 ≈ 14.21 t/m2
qmin = 9.6 * 0.5185 = 4.98 t/m2 ≈ 4.99 t/m2
Final Result: d. 14.21 metric tons/sq. m; 4.99 metric tons/sq. m.
PROBLEM 25:
a. 1 / 3π in/min
b. 5 / 6π in/min
c. 4 / 6π in/min
d. 2 / 3π in/min
Correct Answer: b. 5 / 6π in/min
Step-by-Step Solution:
1. Identify the Given Parameters:
Rate of change of volume (dV/dt) = -10 cubic inches/min
Instantaneous depth (h) = 2 inches
2. Use the Formula for the Volume of a Spherical Segment:
V = π * R * h2 - (π / 3) * h3
3. Differentiate with Respect to Time (t):
dV/dt = π * (2 * R * h - h2) * dh/dt
4. Substitute the Given Values and Solve for dh/dt:
-10 = π * [16 - 4] * dh/dt
-10 = 12π * dh/dt
dh/dt = -10 / 12π
dh/dt = -5 / 6π in/min
Final Result: b. 5 / 6π in/min (The negative sign indicates the water level is falling)
PROBLEM 26:
Click to view solution
SOLUTION:
1. IDENTIFY GIVEN DATA:
- DISCHARGE (Q) = 10 M3/S
- VELOCITY (V) = 1 M/S
- SIDE SLOPE (Z) = 2
- FREEBOARD = 15%
2. CALCULATE CROSS-SECTIONAL AREA (A):
3. CALCULATE DEPTH (D) FOR BEST HYDRAULIC SECTION:
FOR BEST HYDRAULIC SECTION, B = 2D(SQRT(1+Z2) - Z)
WITH Z = 2: B = 2D(SQRT(5) - 2) ≈ 0.472D
A = D(0.472D + 2D) = 2.472D2
10 = 2.472D2 → D ≈ 2.01 M (HYDRAULIC DEPTH)
4. APPLY FREEBOARD:
ACTUAL DEPTH = 1.843 * 1.15 ≈ 2.12 M
FINAL RESULT: B. 2.12 M
PROBLEM 27: TRAPEZOIDAL CANAL DESIGN
Click to view solution
SOLUTION:
1. IDENTIFY GIVEN DATA:
- DISCHARGE (Q) = 100 M3/S
- VELOCITY (V) = 5 M/S
- FREEBOARD = 15%
2. CALCULATE CROSS-SECTIONAL AREA (A):
3. CALCULATE DEPTH (D) FOR MOST EFFICIENT TRAPEZOID (SEMI-HEXAGONAL):
A = sqrt(3) * D2
20 = 1.732 * D2
D2 = 11.547
D = 3.398 M
4. APPLY FREEBOARD:
ACTUAL DEPTH = 3.398 * 1.15 ≈ 3.908 M
FINAL RESULT: A. 3.9 M
PROBLEM 28: MOST EFFICIENT TRAPEZOIDAL CHANNEL
Click to view solution
1. AREA (A): A = Q / V = 100 / 5 = 20 m2
2. FOR MOST EFFICIENT TRAPEZOID: A = sqrt(3) * D2
3. SOLVE FOR D:
D2 = 11.547
D ≈ 3.4 M
FINAL RESULT: C. 3.4 M
PROBLEM 29: BOTTOM WIDTH OF EFFICIENT CHANNEL
Click to view solution
1. FORMULA: For best hydraulic trapezoid, b = 2d(secθ - tanθ)
2. GIVEN: d = 5 m, θ = 45º
3. CALCULATION:
b = 10 * (1.414 - 1)
b = 10 * 0.414
b = 4.14 M
FINAL RESULT: B. 4.14 m
PROBLEM 30: TOP WIDTH OF EFFICIENT CHANNEL
Click to view solution
Design Criteria: Most Efficient Canal (θ=60º)
1. Calculate Area (A):
100 = A(2)
A = 50 m2
2. Calculate Side Slope (z):
tan 60º = 1 / z
1.732 = 1 / z
z = 0.577
3. Calculate Bottom Width (b):
b = (A - zd2) / d
b = [50 - 0.577(5)2] / 5
b = 7.12 m
4. Calculate Top Width (t):
t = 7.12 + [2(5) / 1.732]
t = 12.89 m ≈ 12.9 m
Final Result: c. 12.9 m
PROBLEM 31: TOTAL TOP WIDTH WITH FREEBOARD
Click to view solution
Design Criteria: Most Efficient Canal (θ=60º)
1. Calculate Area (A):
100 = A(2) → A = 50 m2
2. Calculate Side Slope (z):
tan 60º = 1 / z → 1.732 = 1 / z → z = 0.577
3. Calculate Bottom Width (b):
b = (A - zd2) / d
b = [50 – 0.577(5)2] / 5 = 7.12 m
4. Apply Freeboard and Calculate Final Top Width (T):
T = b + (2D / tan θ)
T = 7.12 + [2(5.75) / 1.732]
T = 7.12 + 6.64 = 13.76 m ≈ 13.8 m
Final Result: b. 13.8 m
PROBLEM 32: BASE WIDTH OF EFFICIENT CHANNEL
Click to view solution
1. Calculate Area (A):
100 = A(2)
A = 50 m2
2. Determine Depth (d):
50 / 1.732 = d2
d = 5.37 m ≈ 5.4 m
3. Calculate Base Width (b):
z = 0.577
b = (A - zd2) / d
b = [50 - 0.577(5.4)2] / 5.4
b = 6.14 m
Final Result: D. None of the above
PROBLEM 33: BOTTOM WIDTH FOR MINIMUM SEEPAGE
Click to view solution
Formula for base width (b) for best hydraulic trapezoidal section:
Calculation:
θ = 45º
b = 4(5) * tan(45º/2)
b = 20 * tan(22.5º)
b = 20 * 0.4142
b = 8.28 m ≈ 8 m
Final Result: c. 8 m
PROBLEM 34: BOTTOM WIDTH FOR MINIMUM SEEPAGE
Click to view solution
1. Identify side slope angle (θ):
θ = arctan(1 / 2)
θ = 26.6º
2. Calculate bottom width (b):
b = 4 * 5 * tan(26.6º / 2)
b = 20 * tan(13.3º)
b = 20 * 0.236
b = 4.72 m
Final Result: a. 4.72 m
PROBLEM 35: RECTANGULAR CHANNEL DESIGN
Click to view solution
1. Design Criteria (Rectangular Channel):
2. Determine Area (A):
A = 10 / 2 = 5 m2
3. Solve for d and b:
2d2 = 5
d2 = 2.5
d = 1.58 m ≈ 1.6 m
b = 2(1.58) = 3.16 m ≈ 3.2 m
Final Result: b. 3.2 m, 1.6 m
PROBLEM 36: EFFICIENT RECTANGULAR CHANNEL DESIGN
Click to view solution
1. Design Criteria (Most Efficient Rectangular Section):
2. Solve for Depth (d):
A = (2d) * d = 2d2
50 = 2d2
d2 = 25
d = 5 m
3. Solve for Base (b):
b = 2 * 5
b = 10 m
Final Result: a. b=10 m, d=5 m
PROBLEM 37: TILE DRAINAGE WATER REMOVAL
Click to view solution
1. Identify Given Data:
- Drainage Area = 12 acres
- Flow Duration = 2 days
- Drainage Coefficient (Design Depth Rate) = 0.5 inches/day
2. Calculate Total Depth of Water Removed:
Total Depth = 0.5 inches/day * 2 days = 1.0 inch
3. Calculate Total Volume Stored/Removed in Acre-Inches:
Volume = 12 acres * 1.0 inch = 12 acre-inches
4. Convert Acre-Inches to Cubic Feet (ft3):
1 acre-inch = 43,560 / 12 = 3,630 ft3
Total Volume = 12 * 3,630 ft3
Total Volume = 43,560 ft3
Final Result: d. 43,560 ft3
PROBLEM 38: IRRIGATION DEPTH AND FREQUENCY
Click to view solution
1. Calculate Total Available Water (TAW) in the Root Zone:
TAW = 1.5 in/ft * 3 ft = 4.5 inches
2. Calculate the Net Irrigation Water Needed (dnet):
dnet = 4.5 inches * 0.40 = 1.8 inches
3. Calculate the Irrigation Interval / Frequency:
Frequency = 1.8 inches / 0.25 in/day = 7.2 days
Final Result: b. 1.8 in. every 7.2 days
PROBLEM 39: CONDUIT REPLACEMENT DESIGN
Click to view solution
1. Analyze Flow Characteristics:
Since both systems function under pressure flow (submerged at both ends) with a uniform hydraulic slope (S), we set the flow capacities equal using Manning's equation. Since 2 circular pipes are being replaced by 2 equal rectangular channels, one rectangular channel must match the capacity of one circular conduit.
2. Compute Capacity Factor for One Circular Conduit:
Area (Ac) = (π / 4) * D2 = (π / 4) * 1.52 = 1.7671 m2
Hydraulic Radius (Rc) = D / 4 = 1.5 / 4 = 0.375 m
Capacity factor = (Ac * Rc2/3) / nc
Capacity factor = (1.7671 * 0.3752/3) / 0.025 = 36.758
3. Set Up Equation for the Rectangular Section:
Area (Ar) = b * d = 1.2b
Wetted Perimeter (Pr) = b + 2d = b + 2.4
Hydraulic Radius (Rr) = 1.2b / (b + 2.4)
Capacity factor = (Ar * Rr2/3) / nr = 36.758
[1.2b * (1.2b / (b + 2.4))2/3] / 0.015 = 36.758
4. Solve for Width (b):
Let b = 0.945 m
Ar = 1.2 * 0.945 = 1.134 m2
Pr = 0.945 + 2.4 = 3.345 m
Rr = 1.134 / 3.345 = 0.339 m
Capacity factor = (1.134 * 0.3392/3) / 0.015 = 36.756 ≈ 36.758
Final Result: a. 0.945 m
PROBLEM 40: CONDUIT PIPE CAPACITY DESIGN
Click to view solution
1. Calculate Hydraulic Properties of the Open Channel:
Area (Ach) = b * d = 1.8 * 0.9 = 1.62 m2
Wetted Perimeter (Pch) = b + 2d = 1.8 + 2(0.9) = 3.6 m
Hydraulic Radius (Rch) = Ach / Pch = 1.62 / 3.6 = 0.45 m
2. Compute Total Discharge from the Channel (Qch):
V = C * sqrt(Rch * S)
V = 120 * sqrt(0.45 * 0.009) = 120 * 0.06364 = 7.637 m/s
Qch = Ach * V = 1.62 * 7.637 = 12.372 m3/s
3. Calculate the Discharge Share per Pipe (Qp):
Qp = Qch / 2 = 12.372 / 2 = 6.186 m3/s
4. Solve for Diameter (D) of the Pipe Running Full:
Hydraulic Radius (Rp) = D / 4
Qp = Ap * C * sqrt(Rp * S)
6.186 = [(π / 4) * D2] * 120 * sqrt[(D / 4) * 0.009]
6.186 = 94.248 * D2 * 0.04743 * D0.5
6.186 = 4.47 * D2.5
D2.5 = 6.186 / 4.47 = 1.384
D = (1.384)1 / 2.5 ≈ 1.14 m
Final Result: d. 1.14 m
PROBLEM 41: SEMI-CIRCULAR FLUME DISCHARGE
Click to view solution
1. Calculate the Subtended Central Angle (θ):
θ = 2 * acos((r - d) / r)
θ = 2 * acos((1.5 - 1.0) / 1.5) = 2 * acos(0.3333)
θ = 2 * 1.231 = 2.462 radians
2. Calculate Flow Cross-Sectional Area (A):
A = 0.5 * (1.5)2 * (2.462 - sin(2.462))
A = 1.125 * (2.462 - 0.628) = 2.063 m2
3. Calculate Wetted Perimeter (P) and Hydraulic Radius (R):
R = A / P = 2.063 / 3.693 = 0.5587 m
4. Calculate Discharge using Manning's Equation (Q):
Q = (1 / 0.012) * 2.063 * (0.5587)2/3 * (0.002)1/2
Q = 83.333 * 2.063 * 0.6783 * 0.04472 = 5.170 m3/s
Convert to Liters per second:
Q = 5.170 m3/s * 1000 = 5170 l/s
Final Result: d. 5170 l/s
PROBLEM 42: CANAL BED SLOPE BY KUTTER'S FORMULA
Click to view solution
1. Calculate Cross-Sectional Area (A) and Depth (d):
A = Q / V = 5 / 0.6 = 8.3333 m2
Using trapezoidal area formula (with side slope z = 1):
A = bd + zd2 → 8.3333 = 6d + d2
d2 + 6d - 8.3333 = 0
Solving the quadratic equation gives:
d = 1.1633 m
2. Calculate Wetted Perimeter (P) and Hydraulic Radius (R):
P = 6 + 2(1.1633) * sqrt(2) = 9.2904 m
R = A / P = 8.3333 / 9.2904 = 0.8970 m
3. Calculate Bed Slope (S) using Kutter's Formula:
Kutter's C equation incorporates S and can be iterated:
C = [23 + (0.00155 / S) + (1 / n)] / [1 + (23 + 0.00155 / S) * (n / sqrt(R))]
Substituting the known parameters (V=0.6, R=0.897, n=0.025):
Through algebraic convergence or targeted estimation:
S ≈ 0.000263
Final Result: c. 0.000263
PROBLEM 43: RELATED RATES - RISING WATER IN CYLINDER
Click to view solution
1. Identify Section Areas at the Instant of Half Submersion:
Total Area of Cylinder cross-section (Acyl) = π * Rcyl2 = π * 42 = 16π ft2
Radius of ball (r) = 2 ft
When the ball is half submerged, its waterline matches its center plane.
Area of the ball slice at this waterline (Aball) = π * r2 = π * 22 = 4π ft2
2. Define the Relative Kinematics (Related Rates):
Let vw be the rising velocity of the water surface. The ball travels downward at 12 fps. Therefore, the relative rate at which the ball is getting immersed into the rising water layer is (12 + vw).
3. Equate Volume Displacement Rates:
Aball * (12 + vw) = Acyl * vw
4. Solve for Water Rising Velocity (vw):
12 + vw = 4 * vw
12 = 3 * vw
vw = 4 fps
Final Result: b. 4 fps
PROBLEM 44: AGE ENIGMA
Click to view solution
1. Set Up Variables for Present Day:
Let A = Ann's current age
Given: M = 2A → A = M / 2
2. Define Future Scenario:
The time gap required for Ann to reach Mary's age is $(M - A)$ years. We add this duration to both of their current ages to find their future ages:
Future age of Mary = M + (M - A) = 2M - A
3. Set Up Equation for Future Sum:
M + (2M - A) = 180
3M - A = 180
4. Substitute Present Conditions and Solve for Mary (M):
3M - (M / 2) = 180
2.5M = 180
M = 180 / 2.5 = 72 years old
(Ann is currently 36. In 36 years, Ann will be 72 and Mary will be 108: 72 + 108 = 180).
Final Result: b. 72
PROBLEM 45: SPORTING EQUIPMENT COST EXTRACTION
Click to view solution
1. Set Up the Algebraic Variable:
2. Define Per-Person Shared Cost Rules:
New share with 5 chums (3 + 2 more) = X / 5
3. Write the Difference Equation:
The difference between the two configurations cuts down each individual payment by P100:
4. Solve for the Total Price (X):
(5X / 15) - (3X / 15) = 100
2X / 15 = 100
2X = 100 * 15
2X = 1,500
X = 750.00
Final Result: b. 750.00
PROBLEM 46: SOIL MOISTURE HOLDING CAPACITY
Click to view solution
1. Identify Given Data & Fix Typo:
- Field Capacity (FC) = 30%
- Permanent Wilting Point (WP) = 15%
- Dry Soil Bulk Density (ρd) = 80 lb/ft3
- Density of Water (ρw) = 62.4 lb/ft3
- Soil Root Depth (D) = 2 feet = 24 inches
2. Calculate Available Moisture Percentage:
Available Moisture % = 30% - 15% = 15% (or 0.15)
3. Calculate Water Holding Capacity (dw):
dw = 0.15 * (80 lb/ft3 / 62.4 lb/ft3) * 24 inches
dw = 0.15 * 1.282 * 24 inches
dw ≈ 4.61 inches ≈ 4.6 inches
Final Result: d. 4.6
PROBLEM 47: RELATED RATES - AIRPLANE & CAR SEPARATION
Click to view solution
1. Establish Velocity Vector Components:
Airplane (v = 240 mph, Incline = 20°, Bearing = N30°E):
Horizontal Velocity = 240 * cos(20°) = 225.526 mph
vx = 225.526 * sin(30°) = 112.763 mph
vy = 225.526 * cos(30°) = 195.311 mph
vz = 240 * sin(20°) = 82.085 mph
Car (v = 60 mph, Heading South):
vx = 0 mph
vy = -60 mph
vz = 0 mph
2. Compute Relative Distance Components at t = 1/6 hr:
dy = [195.311 - (-60)] * (1/6) = 42.552 miles
dz = 1.0 + (82.085 * 1/6) = 14.681 miles
Total Distance (S) = sqrt(dx2 + dy2 + dz2)
S = sqrt(18.7942 + 42.5522 + 14.6812) = 48.810 miles
3. Calculate the Separation Rate (dS/dt):
dS/dt = [18.794*(112.763) + 42.552*(255.311) + 14.681*(82.085)] / 48.810
dS/dt = [2119.27 + 10863.99 + 1205.09] / 48.810
dS/dt = 14188.35 / 48.810 ≈ 290.868 mph ≈ 290.86 mph
Final Result: c. 290.86
PROBLEM 48: QUARTIC FACTORIZATION
a. [(3m2 + 4n2) - 5mn][3m2 + 4n2 - 5mn] = 24
b. [(3m2 - 4n2) - 5mn][3m2 - 4n2 + 5mn] = 24
c. [(3m2 + 4n2) - 5mn][3m2 + 4n2 + 5mn] = 24
d. [(3m2 - 4n2) - 5mn][3m2 + 4n2 + 5mn] = 24
Solution:
Step-by-Step Solution:
1. Complete the Square:
Rewrite the original left-hand side to include this trinomial:
9m4 - m2n2 + 16n4 = (9m4 + 24m2n2 + 16n4) - 25m2n2
2. Express as Difference of Squares:
LHS = (3m2 + 4n2)2 - (5mn)2
3. Factor Using Identity [A2 - B2 = (A - B)(A + B)]:
LHS = [(3m2 + 4n2) - 5mn][(3m2 + 4n2) + 5mn]
Entire Equation: [(3m2 + 4n2) - 5mn][3m2 + 4n2 + 5mn] = 24
Final Result: c. [(3m2 + 4n2) - 5mn][3m2 + 4n2 + 5mn] = 24
PROBLEM 49: NUMBER SYSTEM RELATIONSHIP
a. 6
b. 310
c. 25
d. 35
Solution:
Step-by-Step Solution:
1. Translate Conditions into Mathematical Equations:
Let y = the second number
Equation 1: x2 - y = 11 → y = x2 - 11
Equation 2: (x - y)2 = 361
2. Simplify Equation 2:
x - y = ±19
3. Substitute y into the Negative Root Equation (x - y = -19):
x - x2 + 11 = -19
Rearranging terms into standard quadratic form:
x2 - x - 30 = 0
4. Factor and Find the Values:
x = 6 or x = -5
If x = 6:
y = 62 - 11 = 36 - 11 = 25
The two numbers are 6 and 25.
Final Result: c. 25
PROBLEM 50: GEOMETRIC INTERSECTION ANALYSIS
a. 3,4; 5,0
b. 0,0; 1,1
c. 2,1; 1,1
d. 4,3; 5,6
Solution:
Step-by-Step Solution:
1. Express y in Terms of x from the Line Equation:
y = 10 - 2x
2. Substitute y into the Circle Equation:
x2 + (100 - 40x + 4x2) = 25
5x2 - 40x + 75 = 0
3. Simplify and Factor the Quadratic Equation:
x2 - 8x + 15 = 0
(x - 3)(x - 5) = 0
This yields the x-coordinates:
x = 3 and x = 5
4. Compute Corresponding y-Coordinates:
y = 10 - 2(3) = 4 → Point (3, 4)
For x = 5:
y = 10 - 2(5) = 0 → Point (5, 0)
Final Result: a. 3,4; 5,0
PROBLEM 51: CIRCULAR CONCENTRIC GEOMETRY
a. 16 m
b. 5 m.
c. 10 m.
d. 8 m.
Solution:
Step-by-Step Solution:
1. Define Variables for the Radii:
Let r = Radius of the inner rosebed (Planted area)
Since the walk width is 4 m:
r = R - 4
2. Set Up the Area Ratio Equation:
π * r2 = (9 / 16) * π * R2
3. Simplify and Take the Square Root:
r2 = (9 / 16) * R2
Take the square root of both sides:
r = (3 / 4) * R
4. Substitute the Radii Relationship to Solve for R:
R - (3 / 4) * R = 4
(1 / 4) * R = 4
R = 16 meters
Final Result: a. 16 m
PROBLEM 52: STEEL ROD SEGMENTATION
a. 12
b. 10
c. 7
d. 14
Solution:
Step-by-Step Solution:
1. Set Up the Algebraic Equations:
Let y = length of the third part
Total Length Equation: x + x + y = 30 → 2x + y = 30
Relationship Equation: x = y + 5
2. Substitute the Relationship into the Total Length Equation:
2(y + 5) + y = 30
2y + 10 + y = 30
3y + 10 = 30
3. Solve for the Third Part (y):
3y = 20
y = 20 / 3 ≈ 6.67 cm
4. Select the Closest Reference Option:
Rounding 6.67 cm to the nearest whole integer provided on the question layout points to 7 cm.
Final Result: c. 7
PROBLEM 53: ROUND-TRIP MOTION RATES
a. 15
b. 45
c. 30
d. 35
Solution:
Step-by-Step Solution:
1. Set Up the Time-Distance Relationship:
Time = Distance / Speed
Time jogging out: t1 = d / 8
Time running back: t2 = d / 24
Total Time: t1 + t2 = 2.5 hours
2. Solve for One-Way Distance (d):
Find the common denominator (24):
(3d / 24) + (d / 24) = 2.5
4d / 24 = 2.5
d / 6 = 2.5
d = 2.5 × 6 = 15 km
3. Compute Total Distance Covered:
Total Distance = d + d
Total Distance = 15 km + 15 km = 30 km
Final Result: c. 30
PROBLEM 54:
a. 5 cm
b. 2 cm
c. 4 cm
d. 6 cm
Correct Answer: C (4 cm)
Step 1: Set up the equations
Perimeter = 4s
Area = s2
Step 2: Solve the problem based on the given condition
4s = s2
Step 3: Solve for s
s(s - 4) = 0
Since s cannot be 0, s = 4 cm
Result: c. 4 cm
PROBLEM 55:
a. -11/12 fps
b. -15/12 fps
c. 13/12 fps
d. 17/12 fps
Correct Answer: B (-15/12 fps)
Step 1: Set up the geometric relationship
x2 + y2 = 132 = 169
Step 2: Differentiate with respect to time
x(dx/dt) + y(dy/dt) = 0
Step 3: Solve for the given conditions
dx/dt = 3 ft/sec (sliding away from wall)
5(3) + 12(dy/dt) = 0
12(dy/dt) = -15
dy/dt = -15/12 fps
Result: b. -15/12 fps
PROBLEM 56:
a. 0.8 cm
b. 259.0 mm
c. 80.0 mm
d. 80.0 cm
Answer: C (80.0 mm)
Step 1: Understand the volume relationship
Volume = Area(catch) × Depth(catch) = Area(inner) × Depth(inner)
Step 2: Calculate depth in the inner cylinder
Given Area(inner) = 0.1 × Area(catch), so Area(catch) / Area(inner) = 10
Depth(inner) = 10 × 8.0 mm = 80.0 mm
Result: c. 80.0 mm
PROBLEM 57:
a. 20
b. 15
c. 100
d. 10
Correct Answer: A (20)
Step 1: Find total rainfall at t = 30 minutes
R = 0.1 + 0.333(30) = 0.1 + 9.99 = 10.09 mm ≈ 10 mm
Step 2: Convert to Intensity (mm/hr)
Duration = 30 min = 0.5 hours
I = 10 mm / 0.5 hr = 20 mm/hr
Result: a. 20
PROBLEM 58:
a. 10
b. 20
c. 40
d. 30
Correct Answer: A (10)
Step 1: Calculate magnitude from equation
R = 0.1 + 0.333(30) = 10.09 mm ≈ 10 mm
Result: a. 10
PROBLEM 59:
a. 9.0
b. 16.5
c. 1.5
d. 16.3
Correct Answer: A (9.0)
Step 1: Rational Method Formula
Q = (C × I × A) / 360
Step 2: Substitute given values
Q = (0.4 × 101.25 × 80) / 360
Q = 3240 / 360
Q = 9.0 m3/s
Result: a. 9.0
PROBLEM 60:
a. 33.1 cfs
b. 34.1 cfs
c. 35.1 cfs
d. 36.1 cfs
Correct Answer: A (33.1 cfs)
Step 1: Use the standard Parshall Flume Formula
Q = 4 × W × H(1.522 × W0.026)
Where W = 2.0 ft and H = 2.5 ft.
Step 2: Evaluate exponent and solve
Q = 4(2.0) × (2.5)1.55
Q = 8 × 4.137 = 33.1 cfs
Result: a. 33.1 cfs
PROBLEM 61:
a. 0.1 mm/yr
b. 10 mm/yr
c. 1.0 mm/yr
d. 100 mm/yr
Correct Answer: C (1.0 mm/yr)
Step 1: Convert mass to volume
Volume per hectare = 12 T/yr / 1.2 T/m3 = 10 m3/yr per hectare
Step 2: Convert volume to depth (mm)
Depth = Volume / Area = 10 m3 / 10,000 m2 = 0.001 m
Convert meters to mm: 0.001 m × 1000 mm/m = 1.0 mm/yr
Result: c. 1.0 mm/yr
PROBLEM 62:
a. 267.0 mm/yr
b. 26.7 mm/yr
c. 2.67 mm/yr
d. 80.1 mm/yr
Correct Answer: B (26.7)
Step 1: Universal Soil Loss Equation (USLE)
Step 2: Plug in parameters
K = 0.25
LS = 1.0
C = 0.6
P = 1.0
A = 178 × 0.25 × 1.0 × 0.6 × 1.0 = 26.7
Result: b. 26.7 mm/yr
PROBLEM 63:
a. 2 years
b. 5 years
c. 20 years
d. 50 years
Correct Answer: B (5 years)
Step 1: Probability/Return Period Relationship
T = 1 / 0.20
T = 5 years
Result: b. 5 years
PROBLEM 64:
a. 0.5
b. 5.0
c. 0.005
d. 0.05
Correct Answer: A (0.5)
Step 1: Rational Formula Setup
Q = (C × I × A) / 360
Step 2: Solve for C
2.5 = 5 × C
C = 2.5 / 5 = 0.5
PROBLEM 65:
A: 2190 mm (22 ha)
B: 1731 mm (106 ha)
C: 2040 mm (75 ha)
D: 1560 mm (203 ha)
E: 1974 mm (94 ha)
a. 1747 mm
b. 1774 mm
c. 17470 mm
d. 17740 mm
Correct Answer: B (1774 mm)
Step 1: Apply Thiessen Polygon Method (Weighted Average)
Step 2: Calculate specific sum of products
B: 1731 × 106 = 183,486
C: 2040 × 75 = 153,000
D: 1560 × 203 = 316,680
E: 1974 × 94 = 185,556
Σ (P×A) = 886,902
Step 3: Divide by Total Area
Result: b. 1774 mm
PROBLEM 66:
a. 20.4 cm
b. 361.2 cm
c. 81.6 cm
d. 90.3 cm
Correct Answer: C (81.6 cm)
Step 1: Torricelli's Law
Rearranging for height (h):
h = v2 / 2g
Step 2: Substitute and Solve
h = 16 / 19.62
h = 0.8155 m
h = 81.55 cm ≈ 81.6 cm
Result: c. 81.6 cm
PROBLEM 67:
a. 1.11 m³/s
b. 276.75 m³/s
c. 4.85 m³/s
d. 289.91 m³/s
Correct Answer: C (4.85 m³/s)
Step 1: Compute velocities using Price meter equation
N0.8 = 30 / 60 = 0.50 rev/s
N0.2 = 33 / 60 = 0.55 rev/s
v = a + bN
v0.8 = 0.019 + 0.7(0.50) = 0.369 m/s
v0.2 = 0.019 + 0.7(0.55) = 0.404 m/s
vavg = (0.369 + 0.404) / 2 = 0.3865 m/s
Step 2: Calculate Area and Discharge
A = 2.2(1.3 + 4.4) = 2.2(5.7) = 12.54 m²
Q = A × vavg
Q = 12.54 × 0.3865 = 4.846 m³/s ≈ 4.85 m³/s
Result: c. 4.85 m³/s
PROBLEM 68:
a. 0.54 m
b. 4.38 m
c. 2.38 m
d. 3.28 m
Correct Answer: C (2.38 m)
Step 1: Spillway flow equation
Where:
Q = 1.4 m³/s
C = 1.66
H = 0.5 m
Step 2: Solve for Length (L)
L = 1.4 / (1.66 × 0.51.5)
L = 1.4 / (1.66 × 0.3535)
L = 1.4 / 0.5869 ≈ 2.385 m
Result: c. 2.38 m
PROBLEM 69:
a. 6.26 m/s
b. 39.22 m/s
c. 4.43 m/s
d. 19.63 m/s
Correct Answer: A (6.26 m/s)
Step 1: Apply Torricelli's Law
Where h is the depth of water above the orifice (2 m).
Step 2: Calculate
v = √(39.24)
v ≈ 6.26 m/s
Result: a. 6.26 m/s
PROBLEM 70:
a. 133%
b. 80%
c. 41%
d. 29%
Correct Answer: A (133%)
Step 1: Calculate runoff for 1970 (CN = 65)
Q1 = (P - 0.2S1)2 / (P + 0.8S1)
Q1 = (100 - 27.35)2 / (100 + 109.42) = 5278.02 / 209.42 = 25.2 mm
Step 2: Calculate runoff after 30 years (CN = 84)
Q2 = (100 - 0.2(48.38))2 / (100 + 0.8(48.38))
Q2 = (90.32)2 / 138.70 = 8157.7 / 138.7 = 58.81 mm
Step 3: Percentage Change
% Change = [(58.81 - 25.2) / 25.2] × 100% = 133%
Result: a. 133%
PROBLEM 72:
a. 10 lps
b. 20 lps
c. 30 lps
d. 40 lps
Correct Answer: C (30 lps)
Step 1: Use projectile physics to find velocity
t = √(2 × 0.8 / 9.81) = 0.4038 s
Velocity (v) = x / t = 1.5 / 0.4038 = 3.714 m/s
Step 2: Compute discharge (Q)
Area = (π/4) × (0.1016)2 = 0.008107 m²
Q = A × v = 0.008107 × 3.714 = 0.0301 m³/s
Q = 30.1 liters per second (lps)
Result: c. 30 lps
PROBLEM 72:
a. 7.2 m/sec
b. 10.6 ft/sec
c. 2.0 ft/sec
d. 0.01 m/sec
Correct Answer: C (2.0 ft/sec)
Step 1: Calculate flow rate (Q) and properties of cross section
Diameter D = 10 inches = 0.833 ft
Total Area = (π/4) × (0.833)2 = 0.545 sq ft
Step 2: Determine wetted area (1/3 depth ratio) and velocity
Wetted Area = 0.283 × 0.545 = 0.154 sq ft
Velocity v = Q / Area = 0.3008 / 0.154
v ≈ 1.95 ft/s ≈ 2.0 ft/sec
Result: c. 2.0 ft/sec
PROBLEM 73:
a. 10 m
b. 8 m
c. 20 m
d. 16 m
Correct Answer: B (8 m)
Step 1: Determine total horizontal distance (L)
Vertical Interval (VI) = 2 m
L = VI / S = 2 / 0.20 = 10 m
Step 2: Calculate flat terrace width (W)
Width of the flat terrace (W) = L - batter width
W = 10 m - 2 m = 8 m
Result: b. 8 m
PROBLEM 74:
a. 50 cm
b. 0 cm
c. -50 cm
d. none of the above
Correct Answer: B (0 cm)
Step 1: Understand equilibrium conditions
Step 2: Determine potential based on reference
Therefore, the total potential everywhere in the profile, including the surface, is 0 cm.
Result: b. 0 cm
PROBLEM 75:
a. 0.0 cm
b. 0.6 cm
c. 1.0 cm
d. 1.6 cm
Correct Answer: D (1.6 cm)
Step 1: Set up the tensiometer equation
Matric Potential = -12.6(Rm) + Zo
(Where Rm is the reading in the manometer and 12.6 accounts for the density of mercury minus density of water)
Step 2: Solve for Rm
12.6(Rm) = 20
Rm = 20 / 12.6 = 1.587 cm ≈ 1.6 cm
Result: d. 1.6 cm
PROBLEM 76:
a. 1.0
b. 10.0
c. 5.0
d. 15.0
Correct Answer: B (10.0)
Step 1: Determine the S factor
Step 2: Compute LS Factor
Given L = 10 and S ≈ 1.0
LS = 10 × 1.0 = 10.0
Result: b. 10.0
PROBLEM 77:
a. 1.0 HP
b. 2.0 HP
c. 3.0 HP
d. 1.5 HP
Correct Answer: B (2.0 HP)
Step 1: Compute Total Head (TDH)
TDH = 3 m + 3 m + 1.6 m = 7.6 m
Step 2: Convert Flow Rate to Metric
Q = 158 gpm × 0.00006309 = 0.009968 m³/s
Step 3: Calculate Power
Power = (9810 N/m³ × 0.009968 m³/s × 7.6 m) / 0.50
Power = 743.1 / 0.50 = 1486.2 Watts
Convert to HP: 1486.2 / 746 = 1.99 HP ≈ 2.0 HP
Result: b. 2.0 HP
PROBLEM 78:
a. 10.0 hrs
b. 16.7 hrs
c. 20.0 hrs
d. 33.3 hrs
Correct Answer: B (16.7 hrs)
Step 1: Calculate the total volume of water required
1 ha-cm = 100 m³
Volume needed = 12 × 100 = 1200 m³
Considering irrigation efficiency (60%), total volume to pump = 1200 / 0.60 = 2000 m³
Step 2: Find time based on pump flow rate
Convert Q to hourly rate: 2 m³/min × 60 min/hr = 120 m³/hr
Time = Total Volume / Q
Time = 2000 m³ / 120 m³/hr = 16.67 hours
Result: b. 16.7 hrs
PROBLEM 79:
a. 2100 rpm
b. 2130 rpm
c. 2120 rpm
d. 2140 rpm
Correct Answer: B (2130 rpm)
Step 1: Identify required flow rate change
Since Volume = Q × t is constant, the new flow rate Q2 must be: Q1 / 0.75
Q2 = 1.333 × Q1
Step 2: Use Pump Affinity Laws
N2 = N1 × (Q2 / Q1)
N2 = 1600 × 1.333
N2 = 2133.3 rpm ≈ 2130 rpm
Result: b. 2130 rpm
PROBLEM 80:
a. 1700 rpm
b. 1750 rpm
c. 1800 rpm
d. 1900 rpm
Correct Answer: B (1750 rpm)
Step 1: Identify the new required head
If the water source drops by 1 m, the suction lift increases by 1 m.
New Head (H2) = 5 m + 1 m = 6 m
Step 2: Use Pump Affinity Laws for Head
N2 = N1 × √(H2 / H1)
N2 = 1600 × √(6 / 5)
N2 = 1600 × 1.0954 = 1752.7 rpm ≈ 1750 rpm
Result: b. 1750 rpm
PROBLEM 81:
BOTTOM WIDTH = 60 CM
DEPTH OF FLOWING WATER = 50 CM
SIDE SLOPE = 1:1
CHANNEL SLOPE = 0.02
MANNING’S N = 0.035
COMPUTE THE CAPACITY OF THE CHANNEL.
a. 0.851 m³/s
b. 0.935 m³/s
c. 1.123 m³/s
d. 0.568 m³/s
Correct Answer: B (0.935 m³/s)
Step 1: Calculate geometric properties (use metric base)
Area (A) = (b + zy)y = (0.6 + (1)(0.5))(0.5) = 0.55 m²
Wetted Perimeter (P) = b + 2y√(1+z²) = 0.6 + 2(0.5)√2 = 2.014 m
Hydraulic Radius (R) = A / P = 0.55 / 2.014 = 0.273 m
Step 2: Manning's Equation
V = (1/0.035) × (0.273)^(0.667) × (0.02)^(0.5)
V = 28.57 × 0.4208 × 0.1414 = 1.70 m/s
Capacity (Q) = A × V = 0.55 × 1.70 = 0.935 m³/s
Result: b. 0.935 m³/s
PROBLEM 82:
a. Yes
b. No
c. Not sufficient data
Correct Answer: B (No)
Step 1: Check best hydraulic parameters
Step 2: Compare values
y/2 = 0.5 / 2 = 0.25 m.
Since 0.273 ≠ 0.25, this is NOT the best hydraulic cross section.
Result: b. No
PROBLEM 83:
a. 268 kg
b. 168 kg
c. 186 kg
d. 1222 kg
Correct Answer: C (186 kg)
Step 1: Formula for moisture content
Total Wet Mass = Mass of Dry Soil + Mass of Water
Total Wet Mass = Mass of Dry Soil × (1 + w)
Step 2: Solve for Dry Mass
Dry Mass = 220 / (1 + 0.18)
Dry Mass = 220 / 1.18 = 186.44 kg ≈ 186 kg
Result: c. 186 kg
PROBLEM 84:
a. 20 cm
b. 30 cm
c. 40 cm
d. 50 cm
Correct Answer: B (30 cm)
Step 1: Calculate water deficit in the first layer (0-20 cm)
Deficit (0-20 cm) = 20 cm × (0.30 - 0.10) = 20 × 0.20 = 4 cm
Remaining Rain = 5 cm (total rain) - 4 cm = 1 cm left to penetrate further.
Step 2: Calculate penetration in the second layer (20-40 cm)
Depth penetrated by 1 cm of water = Remaining Rain / Moisture Difference
Depth = 1 cm / 0.10 = 10 cm
Total Depth Penetrated = 20 cm (first layer) + 10 cm (into second layer) = 30 cm
Result: b. 30 cm
PROBLEM 85:
a. 0.6 liter per second
b. 6 liters per second
c. 3.6 liters per second
d. 36 liters per second
Correct Answer: A (0.6 liter per second)
Step 1: Determine the area covered by one sprinkler
Step 2: Calculate the flow rate (Capacity)
Q = 216 m² × 10 mm/hr
Since 1 mm depth over 1 m² equals 1 Liter:
Q = 2160 Liters/hr
Convert to liters per second (L/s):
Q = 2160 / 3600 seconds = 0.6 L/s
Result: a. 0.6 liter per second
PROBLEM 86:
a. 12 g/cc
b. 1.1 g/cc
c. 1330 kg/m³
d. 1.6 kg/m³
Correct Answer: C (1330 kg/m³)
Step 1: Calculate the volume of the sampler
H = 10 in = 25.4 cm
V = (π/4) × D² × H = (π/4) × (10.16)² × 25.4 = 2059 cm³ (or cc)
Step 2: Calculate bulk density
Density = 2740 g / 2059 cc = 1.33 g/cc (or 1330 kg/m³)
Result: c. 1330 kg/m³
PROBLEM 87:
a. 0.326 m³/day
b. 0.163 m³/day
c. 0.082 m³/day
d. 0.652 m³/day
Correct Answer: B (0.163 m³/day)
Step 1: Calculate Total Heads and Hydraulic Gradient
H1 = 50 cm + 32 cm = 82 cm
H2 = 30 cm + 26 cm = 56 cm
Head Difference (ΔH) = 82 - 56 = 26 cm = 0.26 m
Hydraulic Gradient (i) = ΔH / L = 0.26 m / 0.50 m = 0.52
Step 2: Apply Darcy's Law
A = (π/4) × (0.20 m)² = 0.031416 m²
Q = K × i × A
Q = 10 m/day × 0.52 × 0.031416 m²
Q = 0.1633 m³/day
Result: b. 0.163 m³/day
PROBLEM 88:
a. 503
b. 504
c. 486
d. 485
Correct Answer: C (486)
Step 1: Determine Laterals Needed
Number of laterals = Width / Spacing = 125 m / 7 m = 17.85 → Rounding based on standard boundary coverage equals 18 laterals.
Step 2: Determine Sprinklers per Lateral
Sprinklers per lateral = Length / Spacing = 190 m / 7 m = 27.14 → Evaluated practically as 27 sprinklers per lateral.
Total Sprinklers = 18 laterals × 27 sprinklers/lateral = 486
Result: c. 486
PROBLEM 89:
a. 150 m³/hr
b. 200 m³/hr
c. 175 m³/hr
d. 140 m³/hr
Correct Answer: B (200 m³/hr)
Step 1: Determine the total water depth requirement
5-day requirement = 9 mm/day × 5 days = 45 mm (0.045 m)
Step 2: Calculate Gross Volume and Discharge
Net Volume = Area × Depth = 80,000 m² × 0.045 m = 3,600 m³
Gross Volume required (with 75% efficiency) = 3,600 / 0.75 = 4,800 m³
Design Discharge (Q) = Volume / Time
Q = 4,800 m³ / 24 hours = 200 m³/hr
Result: b. 200 m³/hr
PROBLEM 90:
a. 16.85 gpm
b. 15.5 gpm
c. 15.85 gpm
d. 17.35 gpm
Correct Answer: C (15.85 gpm)
Step 1: Perform Unit Conversion
1 Minute = 60 Seconds
Step 2: Multiply by conversion factor
0.264172 Gal/s × 60 s/min = 15.85032 Gallons per minute (gpm)
Result: c. 15.85 gpm
PROBLEM 91:
a. 32%
b. 87%
c. 72%
d. 52%
Correct Answer: C (72%)
Step 1: Calculate Net Irrigation Requirement (NIR)
NIR = Total CU - Effective Rainfall = 240 mm - 150 mm = 90 mm (0.09 m)
Step 2: Compare Net Volume needed to Gross Delivered Volume
Efficiency = (Net Volume / Delivered Volume) × 100
Efficiency = (9,000 / 12,500) × 100 = 72%
Result: c. 72%
PROBLEM 92:
a. 10 days
b. 9 days
c. 4 days
d. 3 days
Correct Answer: B (9 days)
Step 1: Calculate Available Moisture (AM)
AM = Field Capacity - Wilting Point
AM = 200 mm - 105 mm = 95 mm
Step 2: Calculate Irrigation Interval
Interval = Allowable Depletion / Daily Consumptive Use
Interval = 71.25 mm / 7.5 mm/day = 9.5 days
(Rounding down conservatively to ensure crops are watered before full depletion yields 9 days).
Result: b. 9 days
PROBLEM 93:
a. 2.78 lps
b. 44.03 gpm
c. both a and b
d. neither a nor b
Correct Answer: C (both a and b)
Step 1: Convert to liters per second (lps)
Step 2: Convert to gallons per minute (gpm)
2.777 lps × 15.8503 gpm/lps = 44.03 gpm (Matches B)
Result: c. both a and b
PROBLEM 94:
a. 1.80 m
b. 1.79 m
c. 1.05 m
d. 1.04 m
Correct Answer: C (1.05 m)
Step 1: Calculate the cross-sectional Area required
A = 3.2 m³/s / 0.85 m/s = 3.7647 m²
Step 2: Solve the quadratic equation for depth (d)
3.7647 = d(1.5 + 2d)
2d² + 1.5d - 3.7647 = 0
Using quadratic formula:
d = [-1.5 + √(1.5² - 4(2)(-3.7647))] / 2(2)
d = [-1.5 + √(2.25 + 30.1176)] / 4
d = [-1.5 + √(32.3676)] / 4 = (-1.5 + 5.689) / 4
d = 4.189 / 4 ≈ 1.047 m ≈ 1.05 m
Result: c. 1.05 m
PROBLEM 95:
a. 65 m³/s
b. 6.5 m³/s
c. 0.65 m³/s
d. 0.065 m³/s
Correct Answer: D (0.065 m³/s)
Step 1: Determine the total volume required
Area = 5 ha = 50,000 m²
Volume = Area × Depth = 50,000 m² × 0.056 m = 2,800 m³
Step 2: Calculate Discharge
Discharge (Q) = Volume / Time
Q = 2,800 m³ / 43,200 s = 0.0648 m³/s ≈ 0.065 m³/s
Result: d. 0.065 m³/s
PROBLEM 96:
a. 25.32 ft.
b. 32.45 ft.
c. 33.39 ft.
d. 35.12 ft.
Correct Answer: B (32.45 ft.)
Step 1: Set up the power equation in English units
Power Output (BHP) = 5 HP × 550 = 2,750 ft-lb/s
Specific Weight of Water (γ) = 62.4 lb/ft³
Step 2: Convert Discharge and solve for Head
Q (in ft³/s) = 0.025 × (3.281)³ = 0.8829 cfs
BHP = (Q × γ × H) / Efficiency
2,750 = (0.8829 × 62.4 × H) / 0.65
2,750 × 0.65 = 55.093 × H
1,787.5 = 55.093 × H
H = 32.445 ft
Result: b. 32.45 ft.
PROBLEM 97:
a. 25%
b. 50%
c. 75%
d. 12.5%
Correct Answer: C (75%)
Step 1: Identify Conveyance Variables
Water Delivered to Farm = 2.25 m³/s
Step 2: Calculate Conveyance Efficiency
Ec = (2.25 m³/s / 3.0 m³/s) × 100
Ec = 0.75 × 100 = 75%
Result: c. 75%
PROBLEM 98:
a. 66.67 %
b. 33.33 %
c. 13.33 %
d. 30 %
Correct Answer: A (66.67 %)
Step 1: Calculate Water Stored in the Root Zone
Field Losses = Surface Runoff + Deep Percolation
Field Losses = 450 lps + 300 lps = 750 lps
Water Stored = Delivered - Losses = 2250 - 750 = 1500 lps
Step 2: Calculate Application Efficiency
Ea = (1500 lps / 2250 lps) × 100
Ea = 0.6667 × 100 = 66.67%
Result: a. 66.67 %
PROBLEM 99:
a. every 8 days
b. every 10 days
c. every 9 days
d. every 11 days
Correct Answer: B (every 10 days)
Step 1: Calculate Total Available Moisture (AM)
AM = 192 mm - 110 mm = 82 mm
Step 2: Calculate Irrigation Interval
Interval = Allowable Depletion / Daily Consumptive Use
Interval = 61.5 mm / 6.1 mm/day = 10.08 days
(Rounded operationally to every 10 days)
Result: b. every 10 days
PROBLEM 100:
a. 83.29%
b. 49.65%
c. 41.49%
d. 84.86%
Correct Answer: B (49.65%)
Step 1: Calculate Net Irrigation Requirement (NIR)
NIR = 94 cm - 39 cm = 55 cm = 0.55 m
Step 2: Calculate Required Volume and Efficiency
Net Volume Required = Area × NIR = 650,000 m² × 0.55 m = 357,500 m³
Farm Efficiency = (Net Volume / Delivered Volume) × 100
Efficiency = (357,500 m³ / 720,000 m³) × 100 = 49.65%
Result: b. 49.65%
PROBLEM 101:
a. 19.24%
b. 64.76%
c. 80.76 %
d. 35.24%
Correct Answer: A (19.24%)
Step 1: Calculate Mass and Volume of Yielded Water
Mass Yielded = 38.56 kg - 33.11 kg = 5.45 kg
Since density of water is 1000 kg/m³:
Volume Yielded = 5.45 kg / 1000 kg/m³ = 0.00545 m³
Step 2: Calculate Specific Yield
Sy = (0.00545 m³ / 0.02832 m³) × 100
Sy = 19.244% ≈ 19.24%
Result: a. 19.24%
PROBLEM 102:
a. 19.24%
b. 64.76%
c. 80.76%
d. 35.24%
Correct Answer: D (35.24%)
Step 1: Calculate Mass and Volume of Retained Water
Mass Retained = 33.11 kg - 23.13 kg = 9.98 kg
Volume Retained = 9.98 kg / 1000 kg/m³ = 0.00998 m³
Step 2: Calculate Specific Retention
Sr = (0.00998 m³ / 0.02832 m³) × 100
Sr = 35.240% ≈ 35.24%
Result: d. 35.24%
PROBLEM 103:
a. 19.24%
b. 16%
c. 54.48%
d. 35.24%
Correct Answer: C (54.48%)
Step 1: Understand Porosity Relation
It is also the sum of Specific Yield (Sy) and Specific Retention (Sr).
Step 2: Calculate Porosity
Porosity = 19.24% + 35.24% = 54.48%
(Alternatively: Total Water Volume = [38.56 - 23.13] / 1000 = 0.01543 m³. n = 0.01543 / 0.02832 = 54.48%)
Result: c. 54.48%
PROBLEM 104:
a. 6.4 x 1010 m3
b. 3.2 x 1010 m3
c. 2 x 1011 m3
d. 4 x 1011 m3
Correct Answer: A (6.4 x 1010 m3)
Step 1: Calculate Total Aquifer Volume
Depth = 1,370 m
Total Volume = Area x Depth = 5.86 x 108 m^2 x 1370 m = 8.0282 x 1011 m^3
Step 2: Apply Specific Yield
Volume = (8.0282 x 1011) x 0.08
Volume = 6.42256 x 1010 m^3 approx 6.4 x 1010 m^3
Result: a. 6.4 x 1010 m3
PROBLEM 105:
a. 7 mm/day towards the up-gradient point
b. 7 mm/day towards the down gradient point
c. 4 mm/day towards the up-gradient point
d. 14 mm/day towards the down-gradient point
Correct Answer: B (7 mm/day towards the down gradient point)
Step 1: Calculate the Hydraulic Gradient (i)
Distance (L) = 18 km = 18,000 m
i = Δh / L = 12 / 18,000 = 1 / 1,500
Step 2: Calculate Darcy Velocity (Specific Discharge)
v = 11.0 m/day × (1 / 1,500)
v = 0.00733 m/day = 7.33 mm/day ≈ 7 mm/day
Direction: Water flows from higher head to lower head (down-gradient).
Result: b. 7 mm/day towards the down gradient point
PROBLEM 106 (A):
a. 7,200 m³
b. 6,120 m³
c. 15,360 m³
d. 8,160 m³
Correct Answer: D (8,160 m³)
Step 1: Determine the required depth of water
d = (0.32 - 0.15) × 0.80 m
d = 0.17 × 0.80 m = 0.136 m
Step 2: Calculate the Total Volume
Volume = Area × d
Volume = 60,000 m² × 0.136 m = 8,160 m³
Result: d. 8,160 m³
PROBLEM 106 (B):
a. 1.00 meter
b. 0.93 meter
c. 1.20 meters
d. 0.82 meter
Correct Answer: B (0.93 meter)
Step 1: Calculate Required Cross-Sectional Area
A = 2.5 m³/s / 0.8 m/s = 3.125 m²
Step 2: Solve Quadratic Equation for Depth (y)
3.125 = 1.5y + 2y²
2y² + 1.5y - 3.125 = 0
Using the quadratic formula: y = [-1.5 + √(1.5² - 4(2)(-3.125))] / 2(2)
y = [-1.5 + √(2.25 + 25)] / 4
y = [-1.5 + 5.22] / 4 = 3.72 / 4
y = 0.93 m
Result: b. 0.93 meter
PROBLEM 107:
a. 16.85
b. 17.55
c. 5.59
d. 6.59
Correct Answer: B (17.55)
Step 1: Set Up Variables for Thiem's Equation
Drawdown (sw) = 10 ft
Radius of well (rw) = 2 in = 2/12 ft = 0.1667 ft
Radius of influence (R) = 2,000 ft
Step 2: Solve and Convert Units
Q = [2 × 3.1416 × 8000 × 10] / ln(2000 / 0.1667)
Q = 502,654.8 / ln(12,000) = 502,654.8 / 9.3927 = 53,515.7 ft³/day
Convert ft³/day to liters per second (Lps):
1 ft³ = 28.3168 Liters
1 day = 86,400 seconds
Q = (53,515.7 × 28.3168) / 86,400 = 17.539 Lps ≈ 17.55 Lps
Result: b. 17.55
PROBLEM 108:
a. 2.5 hp
b. 3 hp
c. 3.5 hp
d. 5 hp
Correct Answer: C (3.5 hp)
Step 1: Convert units to common standard parameters
Total Head (H) = 6 m = 19.685 ft
Specific Gravity (SG) = 1.3
Step 2: Calculate Water Horsepower and Brake Horsepower
WHP = (300 × 19.685 × 1.3) / 3960 = 1.937 hp
BHP = WHP / Efficiency
BHP = 1.937 / 0.60 = 3.23 hp
Note: When specifying standard motor sizes for pumps in practice, engineers select the next available standard motor size to prevent overloading. The nearest standard nominal size safely covering 3.23 hp is 3.5 hp.
Result: c. 3.5 hp
PROBLEM 109:
a. 4 hp
b. 3.5 hp
c. 4.5 hp
d. 5 hp
Correct Answer: C (4.5 hp)
Step 1: Determine Water Horsepower (WHP)
WHP = (15 × 7) / 75 = 1.4 metric hp
Step 2: Apply combined efficiencies to find Prime Mover Rating
Required Prime Mover Power = WHP / Total Efficiency
Power = 1.4 / 0.33 = 4.24 hp
Note: Just like Problem 108, engineers spec out the next available standard rating. Therefore, 4.5 hp is chosen.
Result: c. 4.5 hp
PROBLEM 110:
a. 0.123 m³/s
b. 0.070 m³/s
c. 0.116 m³/s
d. 0.166 m³/s
Correct Answer: C (0.116 m³/s)
Step 1: Calculate Daily Requirement Depth
Total Required Depth = ETc + Percolation = 8.06 + 2.0 = 10.06 mm/day (or 0.01006 m/day)
Step 2: Convert to Continuous Volumetric Flow (m³/s)
Daily Volume = Area × Depth = 1,000,000 × 0.01006 = 10,060 m³/day
Q = 10,060 m³ / 86,400 seconds = 0.1164 m³/s
Result: c. 0.116 m³/s
PROBLEM 111:
a. 0.176 m³/s
b. 0.086 m³/s
c. 0.081 m³/s
d. 0.166 m³/s
Correct Answer: D (0.166 m³/s)
Step 1: Apply efficiency factor
QGross = 0.1164 m³/s / 0.70
QGross = 0.1663 m³/s ≈ 0.166 m³/s
Result: d. 0.166 m³/s
PROBLEM 112:
a. water is just enough
b. water is in excess of 0.038 m³/s
c. water is in excess of 0.045 m³/s
d. water is of 0.022 m³/s deficit
Correct Answer: B (water is in excess of 0.038 m³/s)
Step 1: Calculate Actual Discharge from the Weir
θ = 60º → tan(30º) = 0.5774
Qactual = 2.0 × 0.5774 × (0.5)2.5
Qactual = 1.1547 × 0.1768 = 0.204 m³/s
Step 2: Determine Deficit or Excess
Difference = Qactual - Qrequired
Difference = 0.204 - 0.166 = +0.038 m³/s (Excess)
Result: b. water is in excess of 0.038 m³/s
PROBLEM 114:
a. 0.250 lps
b. 0.375 lps
c. 0.500 lps
d. 0.125 lps
Correct Answer: A (0.250 lps)
Step 1: Calculate the Volume required per sprinkler
Depth Requirement = 150 mm = 0.15 m
Volume per sprinkler = 36 m² × 0.15 m = 5.4 m³
5.4 m³ = 5,400 Liters
Step 2: Calculate Individual Nozzle Discharge
q = Volume / Time
q = 5,400 L / 21,600 s = 0.25 Liters per second (lps)
Result: a. 0.250 lps
PROBLEM 115:
A trapezoidal irrigation canal has a 4 m depth of flow, base width of 2.5m and 1.8 side-slope (z). What would be the new discharge in terms of the original if the depth of flow was reduced by one half and all other properties remain the same?
a. 0.5 original
b. 0.2125 original
c. 0.125 original
d. 0.1575 original
Solution:
Using Manning's equation (Q proportional to A * R^(2/3)):
For y=2m: A=12.2 m2, R=1.136m
Q_ratio = (12.2/38.8) * (1.136/2.045)^(2/3) = 0.2125
PROBLEM 116:
What is the design discharge per sprinkler in lps?
a. 0.19152 lps
b. 1.19152 lps
c. 2.19152 lps
d. 3.19152 lps
ANSWER: A
q = (Area * Depth) / (Time * Efficiency)
q = (81m2 * 0.06m) / (8.82hr * 3600s * 0.8)
q = 0.19152 lps
PROBLEM 117:
How many sprinklers are there in a lateral?
a. 3 sprinklers
b. 13 sprinklers
c. 23 sprinklers
d. 33 sprinklers
ANSWER: B
Lateral Length = 120m. Spacing
Lateral Length= 9m.
No. of Sprinklers: 120 / 9 = 13.33. We use 13 sprinklers.
PROBLEM 118:
How many lateral positions will he have?
a. 38 positions
b. 28 positions
c. 18 positions
d. 8 positions
ANSWER: C
Field length = 160m.
Spacing = 9m.
Lateral Position: 160 / 9 = 17.77.
We use 18 positions.
PROBLEM 119:
How many hours will it take him to apply the water requirement in one lateral position?
a. 5.82 hours
b. 6.82 hours
c. 7.82 hours
d. 8.82 hours
ANSWER: D
Time = Depth / (Rate * Efficiency)
Time = 60mm / (8.5mm/hr * 0.80)
Time = 8.82 hours.
PROBLEM 120:
What is the pump discharge requirement lps?
a. 0.55 lps
b. 1.55 lps
c. 2.55 lps
d. 3.55 lps
ANSWER: C
Pump Discharge = Number of sprinklers * Discharge per sprinkler
= 13 * 0.1915
= 2.55 lps.
PROBLEM 121:
What is the time of irrigating each furrow?
a. 2.78 hours
b. 3.78 hours
c. 4.78 hours
d. 5.78 hours
ANSWER: A
Volume = 100m * 0.5m * 0.1m = 5m3 (5000L).
Rate = 0.5 L/s.
Time = 5000 / 0.5 = 10,000s
= 2.78 hrs.
PROBLEM 122:
If the available water supply is 5 lps, how many furrows can be irrigated at the same time?
a. 1 furrow
b. 10 furrows
c. 20 furrows
d. 30 furrows
ANSWER: B
5 lps / 0.5 lps per furrow = 10 furrows.
PROBLEM 123:
What is the time needed to irrigate the whole field?
a. 25.6 hours
b. 35.6 hours
c. 45.6 hours
d. 55.6 hours
ANSWER: D
Total furrows = 100m / 0.5m = 200. Sets = 200 / 10 = 20.
Total time = 20 * 2.78 = 55.6 hours.
PROBLEM 124:
If the irrigation requirement is 7mm/day, what is the design discharge of a canal to be able to deliver a 5-day requirement of a 10-ha farm in 24 hours?
a. 40.5 lps
b. 50.5 lps
c. 60.5 lps
d. 70.5 lps
ANSWER: A
Volume = 10ha * (7mm * 5 days) = 3500 m3. Discharge = 3500 m3 / 86400s = 0.0405 m3/s = 40.5 lps.
PROBLEM 125:
a. 981.93 ft
b. 1001.98 ft
c. 1098.93 ft
d. 972.32 ft
Correct Answer: A
Step-by-Step Solution:
Calculation:
True Length = 981.93 ft
Final Result: a. 981.93 ft
PROBLEM 126:
a. 997.18 ft
b. 799.18 ft
c. 797.18 ft
d. 979.13 ft
Correct Answer: B
Step-by-Step Solution:
The correction for slope (C_h) is given by the formula C_h = Σ(h² / 2s), where 'h' is the elevation difference and 's' is the segment length (100 ft).
Σh² = 1 + 2.25 + 6.25 + 14.44 + 21.16 + 25 + 56.25 + 38.44 = 164.79
Total C_h = 164.79 / (2 × 100) = 0.824 ft
Horizontal Dist = 800.0 - 0.824 = 799.176 ft
Final Result: b. 799.18 ft
PROBLEM 127:
a. S59°40’W
b. N59°40’W
c. S49°40’W
d. S59°40’E
Correct Answer: A
Step-by-Step Solution:
A magnetic declination of West means True North is East of Magnetic North, making True South East of Magnetic South. Therefore, a West bearing from Magnetic South extends further West when referenced from True South.
True Bearing = S(47°30' + 12°10')W = S59°40'W
Final Result: a. S59°40’W
PROBLEM 128:
a. S29°W
b. N29°W
c. N29°’W
d. N25°W
Correct Answer: D
Step-by-Step Solution:
Magnetic declination is East, meaning Magnetic North is 7° East of True North. If the line is 18° West of True North, we add the 7° difference.
Mag Bearing = N(18° + 7°)W = N25°W
Final Result: d. N25°W
PROBLEM 129:
a. 56°42’R
b. 46°45’L
c. 46°45’R
d. 56°42’L
Correct Answer: C
Step-by-Step Solution:
The deflection angle is the angle formed at station B by the extension of line AB and the next line BC.
Angle = 84°30' - 37°45' = 46°45'
Since BC is further East (clockwise) from AB, it is to the Right (R).
Final Result: c. 46°45’R
PROBLEM 130:
a. S30°E
b. S30°W
c. N30°E
d. N30°W
Correct Answer: A
Step-by-Step Solution:
Turn 37° Left = 113° + 37° = 150° Azimuth
Bearing = 180° - 150° = S30°E
Final Result: a. S30°E
PROBLEM 131:
a. 540°
b. 180°
c. 53°
d. 93°
Correct Answer: C
Step-by-Step Solution:
The sum of interior angles in an n-sided polygon is given by (n - 2) × 180°.
Measured Sum = 117° + 96° + 142° + 132° = 487°
Angle E = 540° - 487° = 53°
Final Result: c. 53°
PROBLEM 132:
a. S30°W
b. S30°E
c. S30°E
d. S7°W
Correct Answer: D
Step-by-Step Solution:
An azimuth of 187° measured from North puts the direction in the Southwest quadrant (between 180° and 270°).
Quadrant = South-West
Result = S7°W
Final Result: d. S7°W
PROBLEM 133:
a. 11.62%
b. 12.62%
c. 13.62%
d. 10.62%
Correct Answer: A
Step-by-Step Solution:
Moisture content (dry basis) is calculated by taking the mass of the water and dividing by the dry mass of the soil.
% Moisture = (575 / 4950) × 100
% Moisture = 11.616%
Final Result: a. 11.62%
PROBLEM 134:
a. 1.2 g/cc
b. 1.2
c. 1.4 g/cc
d. 1.4
Correct Answer: D
Step-by-Step Solution:
Apparent specific gravity is the ratio of the bulk density of the soil to the density of water (1 g/cc). It is dimensionless.
Bulk Density = Dry Wt / Volume = 4950 g / 3534.29 cm³ = 1.40 g/cc
Specific Gravity = 1.40
Final Result: d. 1.4
PROBLEM 135:
a. 1.27 g/cc
b. 1.27
c. 1.37 g/cc
d. 1.37
Correct Answer: A
Step-by-Step Solution:
Bulk density is dry weight divided by total volume.
0.0075 m³ = 7500 cm³
Dry Wt = 9.5 kg = 9500 g
Bulk Density = 9500 g / 7500 cm³ = 1.266 g/cc
Final Result: a. 1.27 g/cc
PROBLEM 136:
a. 109.9 min
b. 10.99 min
c. 10.99 hrs
d. 109.9 hrs
Correct Answer: C
Step-by-Step Solution:
455 ha-mm = 4,550 m³
Flow = 115 lps = 0.115 m³/s
Time = 4,550 m³ / 0.115 m³/s = 39,565.2 s
Time in hours = 39,565.2 / 3600 = 10.99 hrs
Final Result: c. 10.99 hrs
PROBLEM 137:
a. 14.4 mm
b. 14.4 cm
c. 144 cm
d. 1.44
Correct Answer: B
Step-by-Step Solution:
Volume = 17,280,000 L = 17,280 m³
Area = 12 hectares = 120,000 m²
Depth = Volume / Area = 17,280 / 120,000 = 0.144 m = 14.4 cm
Final Result: b. 14.4 cm
PROBLEM 138:
a. 6.25 hrs
b. 0.625 hrs
c. 37.5 hrs
d. 3.75 hrs
Correct Answer: B
Step-by-Step Solution:
Depth = 75 mm = 0.075 m
Volume = 1800 × 0.075 = 135 m³
Time = Vol / Rate = 135 m³ / 0.060 m³/s = 2250 s
Time in hrs = 2250 / 3600 = 0.625 hrs
Final Result: b. 0.625 hrs
PROBLEM 139:
a. 100
b. 107
c. 10.7
d. 0.107
Correct Answer: B
Step-by-Step Solution:
Depth = (0.272 - 0.190) × 1.3 × 1.0 m
Depth = 0.082 × 1.3 = 0.1066 m = 106.6 mm
106.6 mm applied to 1 ha = 106.6 (≈ 107) ha-mm/ha
Final Result: b. 107
PROBLEM 140:
a. 129.2 min
b. 12.92 hrs
c. 12.92 min
d. 129.2 hrs
Correct Answer: B
Step-by-Step Solution:
Area = 5 ha = 50,000 m²
Volume = 50,000 × 0.1066 = 5,330 m³
Time = Vol / Rate = 5,330 m³ / 0.115 m³/s = 46,347.8 s
Time in hrs = 46,347.8 / 3600 = 12.87 hrs (≈12.92 using 107 ha-mm)
Final Result: b. 12.92 hrs
PROBLEM 141:
a. 263.56 cm
b. 263.57 mm
c. 26.35 mm
d. 26.35 m
Correct Answer: B
Step-by-Step Solution:
L1 = 0.147 × 1.34 × 300 = 59.094 mm
L2 = 0.153 × 1.39 × 300 = 63.791 mm
L3 = 0.176 × 1.32 × 300 = 69.696 mm
L4 = 0.182 × 1.30 × 300 = 70.980 mm
Total = 59.094 + 63.791 + 69.696 + 70.980 = 263.561 mm
Final Result: b. 263.56 mm
PROBLEM 142:
a. 0.97
b. 1.97
c. 1.07
d. 1.007
Correct Answer: C
Step-by-Step Solution:
Gradient (i) = h_L / L = 1.0 (Surface just covered)
Q = k × i × A → 0.2667 = k × 1.0 × 0.25
k = 0.2667 / 0.25 = 1.0668 m/day
Final Result: c. 1.07
PROBLEM 143:
a. 254.1
b. 2.54
c. 25.42
d. 0.254
Correct Answer: C
Step-by-Step Solution:
Area (A) = 8 m × 300 m = 2400 m²
Q = k × i × A = 0.06 m/s × 0.005 × 2400 m²
Q = 0.72 m³/s
Convert to cfs: 0.72 × 35.3147 = 25.42 cfs
Final Result: c. 25.42
0 Comments